LAS VEGAS, Nev. (FOX5) – Another round of overnight lane restrictions is coming to the I-515 next week on the Valley’s east side.
It’s part of the Nevada Department of Transportation’s repaving and striping project between Wyoming and Sunset.
Here’s the schedule for the next seven days:
NDOT I-515 IMPROVEMENT PROJECT CLOSURES: JANUARY 14-21, 2024 |
---|
Sunday, January 14 at 8:00 pm to Monday, January 15 at 5:00 am |
Southbound I-515 reduced to one lane between S Nellis Blvd and N Stephanie St |
Northbound I-515 reduced to one lane between S Nellis Blvd and Flamingo Rd |
Northbound I-515 off/onramps at Tropicana Ave and Flamingo Rd offramp closed |
Monday, January 15 at 8:00 pm to Tuesday, January 16 at 5:00 am |
Southbound I-515 reduced to one lane between N Stephanie St and Sunset Rd |
Northbound I-515 reduced to one lane between S Nellis Blvd and Flamingo Rd |
Northbound I-515 off/onramps at Tropicana Ave and Flamingo Rd offramp closed |
Tuesday, January 16 at 8:00 pm to Wednesday, January 17 at 5:00 am |
Southbound I-515 reduced to one lane between Flamingo Rd and S Nellis Blvd |
Southbound I-515 off/onramps at Tropicana Ave and Flamingo Rd onramp closed |
Northbound I-515 reduced to one lane between S Nellis Blvd and Flamingo Rd |
Wednesday, January 17 at 8:00 pm to Thursday, January 18 at 5:00 am |
Southbound I-515 reduced to one lane between Flamingo Rd and S Nellis Blvd |
Southbound I-515 off/onramps at Tropicana Ave and Flamingo Rd onramp closed |
Northbound I-515 reduced to one lane between S Nellis Blvd and Flamingo Rd |
Northbound I-515 off/onramps at Tropicana Ave and Flamingo Rd offramp closed |
Thursday, January 18 at 8:00 pm to Friday, January 19 at 5:00 am |
Southbound I-515 reduced to one lane between S Nellis Blvd and N Stephanie St |
Southbound I-515 off/onramps at Russell Rd closed |
Sunday, January 21 at 8:00 pm to Monday, January 22 at 5:00 am |
Southbound I-515 reduced to one lane between N Stephanie St and Sunset Rd |
Southbound I-515 off/onramps at Galleria Dr closed |
The project consists of replacing mainline concrete slabs, repairing erosion, adding better lighting, and upgrading the barrier railing. It’s designed to improve the safety and rideability of the highway.
For more details on the project, you can visit NDOT’s website.
Copyright 2024 KVVU. All rights reserved.